How to know construction process of Al-formwork?

2018-06-20

Generally construction process is 5 days for one typical floor in China. We have a short article in 'Info center'of our website. Please find and enter to read it.

or

Short introduction: Inspection levels & setting lines → Binding steel bars for columns & walls → Embedded M&E and Plumbing → Acceptance of concealed works → Assembly Al-formwork of wall & column → Installation Al-formwork of beam structure → Rectification and fasten the Al-formwork → Binding steel bars for beam sturctures → Pre-embedded works → Acceptance of concealed works → Pouring concrete and mantaince → Dismantle Al-formwork system → Transferring Al-formwork panels into next floor. Repeat installation flow as last floor.